The team are back on deck after the Christmas New Year break.

 

Design is still progressing, whilst on the ground, progress has been made on the piling platform and early civil works, with the driven piling works to commence next week.

 

The piling rig is due to arrive in Mackay Monday closely followed by the delivery of the pre-cast driven piles making their way up the Bruce Highway.

 

Electrical early works have also commenced with the relocation of the control box for the lighting tower to make way for the new concourse walkway.

 

Structural steel workshop drawings are underway with the larger roof beams already ordered due to long lead times.

 

We thank you for your patience and understanding in advance as we deliver this exciting infrastructure to the Mackay community. Stay tuned for more project updates throughout 2022.

 

 

Principal Contractor profile

 

 

Over our 60-year history we have undertaken numerous significant developments within the sporting, community and hospitality sectors, including the design and construction of the Mackay Aquatic and Recreation Complex. We believe our strong experience, localised knowledge and our talented team are keys to the successful delivery of the Great Barrier Reef Arena.

 

We are a Queensland-owned contractor and are proud of the strong relationships we have with our local subcontractor and supplier market, having delivered a number of high-profile projects in the Mackay & Whitsunday region for Federal, State and Local governments.

 

As the head contractor for the redevelopment of Harrup Park, we’re excited to see the benefits the Great Barrier Reef Arena will bring to the local region.

 

Visit paynters.com.au to learn more about us.

 

 

« of 2 »

January Project Update